Tibco
TB0-123 · Question #121
A TIBCO ActiveMatrix BusinessWorks process uses several upstream activities to build a dynamic SQL statement. Which two activities must be configured to execute this statement? (Choose two.)
The correct answer is C. Query Designer F. JDBC Get Connection. See the full explanation below for the reasoning.
Question
A TIBCO ActiveMatrix BusinessWorks process uses several upstream activities to build a dynamic SQL statement. Which two activities must be configured to execute this statement? (Choose two.)
Options
- ASQL Direct
- BJDBC Query
- CQuery Designer
- DJDBC Connection
- EJDBC Call Procedure
- FJDBC Get Connection
How the community answered
(28 responses)- B4% (1)
- C82% (23)
- D4% (1)
- E11% (3)
Community Discussion
No community discussion yet for this question.