nerdexam
CompTIACompTIA

SY0-701 · Question #84

SY0-701 Question #84: Real Exam Question with Answer & Explanation

The correct answer is B: Scheduled downtime. Scheduled downtime is a planned period of time when a system or service is unavailable for maintenance, updates, upgrades, or other changes. Scheduled downtime gives administrators a set period to perform changes to an operational system without disrupting the normal business ope

Submitted by satoshi_tk· Mar 6, 2026Security Operations

Question

Which of the following best practices gives administrators a set period to perform changes to an operational system to ensure availability and minimize business impacts?

Options

  • AImpact analysis
  • BScheduled downtime
  • CBackout plan
  • DChange management boards

Explanation

Scheduled downtime is a planned period of time when a system or service is unavailable for maintenance, updates, upgrades, or other changes. Scheduled downtime gives administrators a set period to perform changes to an operational system without disrupting the normal business operations or affecting the availability of the system or service. Scheduled downtime also allows administrators to inform the users and stakeholders about the expected duration and impact of

Community Discussion

No community discussion yet for this question.

Full SY0-701 PracticeBrowse All SY0-701 Questions