SY0-701 · Question #443
Which of the following would be the best way to test resiliency in the event of a primary power failure?
The correct answer is D. Production failover. Production failover involves switching to a backup power source or system to ensure that operations continue seamlessly in the event of a primary power failure. This type of testing verifies that the failover mechanisms work as intended under real-world conditions and ensures tha
Question
Which of the following would be the best way to test resiliency in the event of a primary power failure?
Options
- AParallel processing
- BTabletop exercise
- CSimulation testing
- DProduction failover
How the community answered
(52 responses)- A8% (4)
- B4% (2)
- C13% (7)
- D75% (39)
Explanation
Production failover involves switching to a backup power source or system to ensure that operations continue seamlessly in the event of a primary power failure. This type of testing verifies that the failover mechanisms work as intended under real-world conditions and ensures that the system can handle the transition smoothly.