SY0-701 · Question #199
A systems administrator would like to deploy a change to a production system. Which of the following must the administrator submit to demonstrate that the system can be restored to a working state…
The correct answer is A. Backout plan. To demonstrate that the system can be restored to a working state in the event of a performance issue after deploying a change, the systems administrator must submit a backout plan. A backout plan outlines the steps to revert the system to its previous state if the new…
Question
A systems administrator would like to deploy a change to a production system. Which of the following must the administrator submit to demonstrate that the system can be restored to a working state in the event of a performance issue?
Options
- ABackout plan
- BImpact analysis
- CTest procedure
- DApproval procedure
How the community answered
(45 responses)- A89% (40)
- B2% (1)
- C7% (3)
- D2% (1)
Explanation
To demonstrate that the system can be restored to a working state in the event of a performance issue after deploying a change, the systems administrator must submit a backout plan. A backout plan outlines the steps to revert the system to its previous state if the new deployment causes Backout plan: Provides detailed steps to revert changes and restore the system to its previous state in case of issues, ensuring minimal disruption and quick recovery. Impact analysis: Evaluates the potential effects of a change but does not provide steps to revert Test procedure: Details the steps for testing the change but does not address restoring the system to a previous state. Approval procedure: Involves obtaining permissions for the change but does not ensure system recovery in case of issues.