SY0-701 · Question #11
A technician needs to apply a high-priority patch to a production system. Which of the following steps should be taken first?
The correct answer is C. Create a change control request. A change control request is a document that describes the proposed change to a system, the reason for the change, the expected impact, the approval process, the testing plan, the implementation plan, the rollback plan, and the communication plan. A change control request is a…
Question
A technician needs to apply a high-priority patch to a production system. Which of the following steps should be taken first?
Options
- AAir gap the system.
- BMove the system to a different network segment.
- CCreate a change control request.
- DApply the patch to the system.
How the community answered
(35 responses)- A3% (1)
- B9% (3)
- C71% (25)
- D17% (6)
Explanation
A change control request is a document that describes the proposed change to a system, the reason for the change, the expected impact, the approval process, the testing plan, the implementation plan, the rollback plan, and the communication plan. A change control request is a best practice for applying any patch to a production system, especially a high-priority one, as it ensures that the change is authorized, documented, tested, and communicated. A change control request also minimizes the risk of unintended consequences, such as system downtime, data loss, or security breaches.
Community Discussion
No community discussion yet for this question.