nerdexam
CompTIA

SY0-301 · Question #501

Which of the following MOST specifically defines the procedures to follow when scheduled system patching fails resulting in system outages?

The correct answer is B. Change management. Change management is the formal process that governs how changes to IT systems are planned, tested, approved, implemented, and rolled back. A key component of change management is the rollback or back-out plan - a documented procedure that specifies exactly what steps to take if

Security program management and oversight

Question

Which of the following MOST specifically defines the procedures to follow when scheduled system patching fails resulting in system outages?

Options

  • ARisk transference
  • BChange management
  • CConfiguration management
  • DAccess control revalidation

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    94% (48)
  • D
    2% (1)

Explanation

Change management is the formal process that governs how changes to IT systems are planned, tested, approved, implemented, and rolled back. A key component of change management is the rollback or back-out plan - a documented procedure that specifies exactly what steps to take if a scheduled change (like a patch) fails and causes an outage. Risk transference (A) shifts risk to a third party (e.g., insurance) but does not define procedures. Configuration management (C) tracks system configurations but does not define failure response procedures. Access control revalidation (D) is unrelated to patching failures.

Topics

#change management#patch management#rollback procedures#system outage

Community Discussion

No community discussion yet for this question.

Full SY0-301 Practice