SSCP · Question #542
Business Continuity Planning (BCP) is not defined as a preparation that facilitates:
The correct answer is C. the monitoring of threat activity for adjustment of technical controls. Although important, The monitoring of threat activity for adjustment of technical controls is not facilitated by a Business Continuity Planning The following answers are incorrect: All of the other choices are facilitated by a BCP: the continuation of critical business functions
Question
Business Continuity Planning (BCP) is not defined as a preparation that facilitates:
Options
- Athe rapid recovery of mission-critical business operations
- Bthe continuation of critical business functions
- Cthe monitoring of threat activity for adjustment of technical controls
- Dthe reduction of the impact of a disaster
How the community answered
(27 responses)- A4% (1)
- C93% (25)
- D4% (1)
Explanation
Although important, The monitoring of threat activity for adjustment of technical controls is not facilitated by a Business Continuity Planning The following answers are incorrect: All of the other choices are facilitated by a BCP: the continuation of critical business functions the rapid recovery of mission-critical business operations the reduction of the impact of a disaster