Which of the following rules pertaining to a Business Continuity Plan/Disaster Recovery Plan is incorrect?

The correct answer is A. In order to facilitate recovery, a single plan should cover all locations. This statement is incorrect because best practice requires separate BCP/DRP plans for each location or site. A single plan covering all locations becomes unwieldy, location-specific details get buried, and the plan may not address the unique infrastructure, personnel, and…

Submitted by andreas_gr· Apr 18, 2026Incident Response and Recovery

Question

Which of the following rules pertaining to a Business Continuity Plan/Disaster Recovery Plan is incorrect?

Options

  • AIn order to facilitate recovery, a single plan should cover all locations.
  • BThere should be requirements to form a committee to decide a course of action.
  • CIn its procedures and tasks, the plan should refer to functions, not specific individuals.
  • DCritical vendors should be contacted ahead of time to validate equipment can be obtained in

How the community answered

(40 responses)
  • A
    95% (38)
  • C
    3% (1)
  • D
    3% (1)

Explanation

This statement is incorrect because best practice requires separate BCP/DRP plans for each location or site. A single plan covering all locations becomes unwieldy, location-specific details get buried, and the plan may not address the unique infrastructure, personnel, and recovery resources at each site. Having location-specific plans ensures clarity and actionability. The other options reflect correct BCP principles: avoiding dependency on specific individuals (use roles/functions), pre-arranging vendor agreements, and forming decision-making committees.