SK0-005 · Question #594
An administrator is tasked with adding three servers to the company's rack in the datacenter. The rack has 42U total capacity with 5U free. The two top- of-rack switches have two ports free on each. T
Sign in or unlock SK0-005 to reveal the answer and full explanation for question #594. The question stem and answer options stay visible for context.
Question
An administrator is tasked with adding three servers to the company's rack in the datacenter. The rack has 42U total capacity with 5U free. The two top- of-rack switches have two ports free on each. The servers have three NICs and must have redundant network connections. Which of the following would allow the administrator to complete this task?
Options
- AAdd three 1U servers to the rack and two 1U switches. Connect both of the new switches to the
- BAdd three 1U servers and two 1U switches to the rack. Connect the new switches to a free port
- CAdd three 1U servers and a 2U switch to the rack. Connect the new switch to a free port on one
- DAdd three 1U servers to the rack and connect one NIC from each server to one free switchport.