In the context of a Team Increment, every Iteration each team plans, builds, tests, integrates, and?

The correct answer is B. Review their work. B is correct because the standard Iteration cadence in SAFe (Scaled Agile Framework) follows a defined rhythm: plan, build, test, integrate, and review - culminating in an Iteration Review where the team demonstrates completed work to stakeholders and gathers feedback. A…

Iteration Execution

Question

In the context of a Team Increment, every Iteration each team plans, builds, tests, integrates, and?

Options

  • AReorganizes
  • BReview their work
  • CSets new objectives
  • DClears out the backlog

How the community answered

(64 responses)
  • A
    2% (1)
  • B
    92% (59)
  • C
    5% (3)
  • D
    2% (1)

Explanation

B is correct because the standard Iteration cadence in SAFe (Scaled Agile Framework) follows a defined rhythm: plan, build, test, integrate, and review - culminating in an Iteration Review where the team demonstrates completed work to stakeholders and gathers feedback.

  • A (Reorganizes) is wrong - team structure isn't reassessed every Iteration; reorganization is a much rarer, deliberate event.
  • C (Sets new objectives) is wrong - objectives are set during Iteration Planning, not as a closing step; the final step is reviewing what was accomplished.
  • D (Clears out the backlog) is wrong - backlogs are never truly "cleared"; they are continuously refined and reprioritized, not emptied on a schedule.

Memory tip: Think of the Iteration cycle as a story with a beginning and end - it starts with planning and ends with a review. The sequence spells out P-B-T-I-R (Plan, Build, Test, Integrate, Review), which you can remember as "Please Bring The Iteration Report."