nerdexam
Scaled_Agile

SAFE-SSM · Question #32

How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?

Sign in or unlock SAFE-SSM to reveal the answer and full explanation for question #32. The question stem and answer options stay visible for context.

Agile Metrics and Estimation

Question

How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?

Options

  • A1 Iteration
  • B2 Iterations
  • C3 Iterations
  • D4 Iterations

Unlock SAFE-SSM to see the answer

You've previewed enough free SAFE-SSM questions. Unlock SAFE-SSM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#velocity#story points#iteration planning#capacity
Full SAFE-SSM Practice