How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?
Sign in or unlock SAFE-SSM to reveal the answer and full explanation for question #32. The question stem and answer options stay visible for context.
Agile Metrics and Estimation
Question
How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?
Options
- A1 Iteration
- B2 Iterations
- C3 Iterations
- D4 Iterations
Unlock SAFE-SSM to see the answer