nerdexam
Scaled_Agile

SAFE-SSM · Question #32

How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?

The correct answer is C. 3 Iterations. Dividing the total backlog (60 story points) by the team's velocity (20 story points per Iteration) gives exactly 60 ÷ 20 = 3 Iterations, making C correct. Option A (1 Iteration) would only work if the team could complete all 60 points at once, which exceeds their velocity…

Agile Metrics and Estimation

Question

How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?

Options

  • A1 Iteration
  • B2 Iterations
  • C3 Iterations
  • D4 Iterations

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    7% (2)
  • C
    90% (27)

Explanation

Dividing the total backlog (60 story points) by the team's velocity (20 story points per Iteration) gives exactly 60 ÷ 20 = 3 Iterations, making C correct. Option A (1 Iteration) would only work if the team could complete all 60 points at once, which exceeds their velocity. Option B (2 Iterations) covers only 40 story points (2 × 20), leaving 20 points unfinished. Option D (4 Iterations) overshoots by one, completing 80 points when only 60 are needed. Memory tip: Think of velocity as a "speed limit" - just divide the total distance (backlog) by the speed (velocity) to get the number of trips (Iterations) required.

Topics

#velocity#story points#iteration planning#capacity

Community Discussion

No community discussion yet for this question.

Full SAFE-SSM Practice