SAFE-SSM · Question #25
What is the intended value of the Backlog Refinement event?
The correct answer is A. The team is able to prepare requirements for Iteration Planning. The intended value of the Backlog Refinement event is that the team is able to prepare requirements for Iteration Planning. Backlog Refinement is an ongoing process where the team collaborates with the Product Owner and other stakeholders to review, split, prioritize, and…
Question
What is the intended value of the Backlog Refinement event?
Options
- AThe team is able to prepare requirements for Iteration Planning
- BThe team aligns on the progress of Iteration Goals
- CThe team is able to commit to a set of goals to be delivered in the Iteration
- DThe team reviews and improves processes before the next Iteration
How the community answered
(47 responses)- A87% (41)
- B6% (3)
- C2% (1)
- D4% (2)
Explanation
The intended value of the Backlog Refinement event is that the team is able to prepare requirements for Iteration Planning. Backlog Refinement is an ongoing process where the team collaborates with the Product Owner and other stakeholders to review, split, prioritize, and estimate the stories in the Team Backlog. One of the main objectives of Backlog Refinement is to ensure that the stories are ready for Iteration Planning, which means they are clear, feasible, testable, and small enough to be completed in a single Iteration. By doing so, the team can improve the quality, efficiency, and effectiveness of their work, as well as deliver value to the customers and the organization.
Topics