SAFE-SPC · Question #97
What activity calls for using ROAM technique?
The correct answer is C. Categorizing program risks during PI Planning. ROAM is a SAFe risk management technique applied specifically during PI Planning, where teams identify program-level risks and collaboratively categorize each one as Resolved, Owned, Accepted, or Mitigated - making C the correct answer. Why the distractors are wrong: A (Program…
Question
What activity calls for using ROAM technique?
Options
- ARefining the Program Backlog.
- BManaging the ART sync.
- CCategorizing program risks during PI Planning.
- DManaging teams by the Release Train Engineer.
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C94% (29)
Explanation
ROAM is a SAFe risk management technique applied specifically during PI Planning, where teams identify program-level risks and collaboratively categorize each one as Resolved, Owned, Accepted, or Mitigated - making C the correct answer.
Why the distractors are wrong:
- A (Program Backlog refinement) uses prioritization techniques like WSJF (Weighted Shortest Job First), not ROAM.
- B (ART Sync) is a recurring coordination ceremony focused on progress and impediment removal - risk categorization is not its purpose.
- D (RTE managing teams) is too vague and describes a general role function; the RTE facilitates ROAM during PI Planning, but ROAM itself is a risk categorization activity, not a team management technique.
Memory tip: Think "ROAM the risks at PI Planning" - risks surface when teams plan together, so you ROAM through them right there to decide each risk's fate before the PI begins.
Topics