SAFE-SPC · Question #97

What activity calls for using ROAM technique?

The correct answer is C. Categorizing program risks during PI Planning. ROAM is a SAFe risk management technique applied specifically during PI Planning, where teams identify program-level risks and collaboratively categorize each one as Resolved, Owned, Accepted, or Mitigated - making C the correct answer. Why the distractors are wrong: A (Program…

PI Planning

Question

What activity calls for using ROAM technique?

Options

  • ARefining the Program Backlog.
  • BManaging the ART sync.
  • CCategorizing program risks during PI Planning.
  • DManaging teams by the Release Train Engineer.

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    94% (29)

Explanation

ROAM is a SAFe risk management technique applied specifically during PI Planning, where teams identify program-level risks and collaboratively categorize each one as Resolved, Owned, Accepted, or Mitigated - making C the correct answer.

Why the distractors are wrong:

  • A (Program Backlog refinement) uses prioritization techniques like WSJF (Weighted Shortest Job First), not ROAM.
  • B (ART Sync) is a recurring coordination ceremony focused on progress and impediment removal - risk categorization is not its purpose.
  • D (RTE managing teams) is too vague and describes a general role function; the RTE facilitates ROAM during PI Planning, but ROAM itself is a risk categorization activity, not a team management technique.

Memory tip: Think "ROAM the risks at PI Planning" - risks surface when teams plan together, so you ROAM through them right there to decide each risk's fate before the PI begins.

Topics

#ROAM#PI Planning#risk management#program risks