SAFE-SPC · Question #80

How does a team calculate its initial velocity during its first PI Planning meeting when teams don't have historic data?

The correct answer is A. Assign 8 points per team member (not counting the Scrum Master and Product Owner) and. In SAFe (Scaled Agile Framework), the standard starting point for teams with no historical data is to assign 8 story points per contributing team member per iteration, explicitly excluding the Scrum Master and Product Owner, whose roles are facilitative rather than…

PI Planning

Question

How does a team calculate its initial velocity during its first PI Planning meeting when teams don't have historic data?

Options

  • AAssign 8 points per team member (not counting the Scrum Master and Product Owner) and
  • BIt is not recommended to calculate velocity until the team has completed its first PI.
  • CAllow teams to establish their own velocity and then roll them up to calculate the velocity of the
  • DAssign 10 points per team member (not counting the Scrum Master and Product Owner) and

How the community answered

(70 responses)
  • A
    89% (62)
  • B
    3% (2)
  • C
    7% (5)
  • D
    1% (1)

Explanation

In SAFe (Scaled Agile Framework), the standard starting point for teams with no historical data is to assign 8 story points per contributing team member per iteration, explicitly excluding the Scrum Master and Product Owner, whose roles are facilitative rather than delivery-focused. This provides a conservative, consistent baseline that avoids overcommitting during the first PI.

Option B is wrong because waiting until after the first PI to calculate velocity would leave the team unable to plan any iterations during PI Planning - some estimate is required to commit to PI Objectives.

Option C is wrong because while teams do establish their own velocity in SAFe, "rolling up" individual velocities to calculate an aggregate team velocity describes an ART-level capacity calculation, not the method for establishing an individual team's initial velocity.

Option D is wrong because 10 points per person is simply not the SAFe-prescribed figure - 8 points is the official recommended default, which already accounts for meetings, overhead, and ramp-up time for newer teams.

Memory tip: Think "8 for the developers, 0 for the facilitators" - 8 points per developer (SM and PO don't count), and SAFe chose 8 because it's conservative enough to build trust and avoid early overcommitment.

Topics

#velocity#PI Planning#team capacity#initial estimation