Question

(Select 2) What is true about budgets in SAFe?

Options

  • ABudgets are allocated to projects.
  • BBudgets are allocated to strategic themes.
  • CBudgets are allocated to portfolios.
  • DBudgets are allocated to teams.
  • EBudgets are allocated to value streams.