SAFE-SPC · Question #24
When is the Solution Demo conducted?
The correct answer is C. At the end of each PI. Option C is correct because in SAFe (Scaled Agile Framework), the Solution Demo occurs at the end of each Program Increment (PI) - typically an 8–12 week timebox. It's held at the Large Solution level to demonstrate all integrated and tested features delivered across multiple…
Question
When is the Solution Demo conducted?
Options
- AOn demand.
- BAt the end of each Sprint.
- CAt the end of each PI.
- DMid-PI.
How the community answered
(24 responses)- A4% (1)
- C92% (22)
- D4% (1)
Explanation
Option C is correct because in SAFe (Scaled Agile Framework), the Solution Demo occurs at the end of each Program Increment (PI) - typically an 8–12 week timebox. It's held at the Large Solution level to demonstrate all integrated and tested features delivered across multiple Agile Release Trains (ARTs) to customers and key stakeholders.
Why the distractors are wrong:
- A (On demand) - The Solution Demo follows a fixed cadence tied to the PI, not an ad hoc schedule.
- B (End of each Sprint) - This describes the System Demo, which occurs at the Iteration/Sprint level within a single ART, not the full solution.
- D (Mid-PI) - Mid-PI is associated with the PI System Demo or status checkpoints, not the Solution Demo.
Memory tip: Think in scope - Sprint → System Demo, PI → Solution Demo. The bigger the timebox, the bigger the demo. "Solution" and "PI" both represent the largest scope in their respective categories, so pair them together.