SAFE-SPC · Question #108

When during PI Planning is the ROAM technique used to categorize program risks?

The correct answer is A. After the final plan review. ROAM (Resolved, Owned, Accepted, Mitigated) is applied after the final plan review because that is when all team plans have been presented and the full set of program-level risks is visible - only then can the group systematically categorize each risk with appropriate ownership…

Agile Product Delivery

Question

When during PI Planning is the ROAM technique used to categorize program risks?

Options

  • AAfter the final plan review
  • BDuring the final plan review
  • CDuring the draft plan review
  • DDuring the management review and problem-solving meeting

How the community answered

(31 responses)
  • A
    87% (27)
  • B
    3% (1)
  • C
    3% (1)
  • D
    6% (2)

Explanation

ROAM (Resolved, Owned, Accepted, Mitigated) is applied after the final plan review because that is when all team plans have been presented and the full set of program-level risks is visible - only then can the group systematically categorize each risk with appropriate ownership and disposition.

Why the distractors are wrong:

  • B (During the final plan review) - The final plan review is for teams to present their plans and surface risks, not to formally categorize them; ROAMing is the structured follow-on step.
  • C (During the draft plan review) - Draft plan review happens at the end of Day 1 and is too early; plans are still being adjusted overnight after management review, so risks aren't finalized yet.
  • D (During management review and problem-solving) - This meeting is where leadership addresses planning conflicts and adjusts scope/resources; it precedes the final plan review entirely and has a different purpose.

Memory tip: Think of ROAM as the closing ceremony of PI Planning - you can only sort risks into buckets once everyone has shown their cards (final plans), so it naturally comes after the last major presentation, not during it.