SAFE-SPC · Question #102
What activity occurs during the program Inspect and Adapt workshop?
The correct answer is A. PI Predictability Measure update. PI Predictability Measure is updated during the Inspect and Adapt (I&A) workshop because it's a core quantitative component of I&A - teams and trains review actual vs. planned PI Objectives to calculate a predictability score, which feeds directly into the I&A problem-solving…
Question
What activity occurs during the program Inspect and Adapt workshop?
Options
- API Predictability Measure update.
- BRoadmap update
- CTeam Iteration Demo
- DBiweekly System Demo
- EIteration Metrics update
How the community answered
(35 responses)- A89% (31)
- B3% (1)
- D3% (1)
- E6% (2)
Explanation
PI Predictability Measure is updated during the Inspect and Adapt (I&A) workshop because it's a core quantitative component of I&A - teams and trains review actual vs. planned PI Objectives to calculate a predictability score, which feeds directly into the I&A problem-solving workshop.
Why the distractors are wrong:
- B (Roadmap update): Roadmap updates happen during PI Planning, not I&A.
- C (Team Iteration Demo): This happens at the end of each Iteration, not at the end of a PI.
- D (Biweekly System Demo): The System Demo occurs every two weeks during a PI; the final System Demo precedes I&A but is a separate event.
- E (Iteration Metrics update): Iteration Metrics are tracked within each Iteration retrospective, not specifically in the I&A workshop.
Memory tip: Think of I&A as a PI-level retrospective - just as a regular retrospective measures how well the team did, I&A measures how predictable the entire train was by comparing planned vs. actual PI Objectives. "Inspect" = measure predictability; "Adapt" = solve problems identified.