Product Management is responsible for "what gets built" as defined by the Vision, Roadmap, and what else?

The correct answer is A. Program Backlog. Option A (Program Backlog) is correct because in SAFe, Product Management owns the three artifacts that define what gets built: the Vision, the Roadmap, and the Program Backlog - which holds the prioritized features waiting to be developed. Together, these three form the…

Agile Product Delivery

Question

Product Management is responsible for "what gets built" as defined by the Vision, Roadmap, and what else?

Options

  • AProgram Backlog
  • BKey stakeholders
  • CCustomers
  • DPI Planning

How the community answered

(42 responses)
  • A
    95% (40)
  • B
    2% (1)
  • D
    2% (1)

Explanation

Option A (Program Backlog) is correct because in SAFe, Product Management owns the three artifacts that define what gets built: the Vision, the Roadmap, and the Program Backlog - which holds the prioritized features waiting to be developed. Together, these three form the complete scope of Product Management's "what" responsibility.

Why the distractors are wrong:

  • B (Key stakeholders) - Stakeholders are inputs to Product Management's decisions, not an artifact that defines what gets built.
  • C (Customers) - Customers provide needs and feedback, but they are not an artifact under Product Management ownership in this triad.
  • D (PI Planning) - PI Planning is an event (a ceremony), not a defining artifact of what gets built; it's where teams plan how to deliver the features from the Program Backlog.

Memory tip: Think of Product Management as owning the "VRP" trio - Vision, Roadmap, Program Backlog. The Program Backlog is the actionable list that connects the long-term Vision and Roadmap to actual work, so it completes the set.

Topics

#Product Management#Program Backlog#Vision#Roadmap