SAFE-SP · Question #32

James is a Product Owner. It is day seven of the Iteration and his team tells him that they may miss their Iteration commitment. What should James do?

The correct answer is C. Ensure the Iteration backlog is accurately prioritized. When a team signals a potential miss mid-Iteration, the Product Owner's proper response is to ensure the Iteration Backlog is accurately prioritized so the most valuable work gets completed first - if anything must be dropped, it should be the lowest-priority items, not…

Agile Product Delivery

Question

James is a Product Owner. It is day seven of the Iteration and his team tells him that they may miss their Iteration commitment. What should James do?

Options

  • ASupport adding an Innovation and Planning Iteration directly after the current Iteration
  • BAgree to add a person from the System Team to complete the work
  • CEnsure the Iteration backlog is accurately prioritized
  • DSupport splitting a Story into a coding story and a testing story, and then moving the testing story

How the community answered

(41 responses)
  • A
    12% (5)
  • B
    7% (3)
  • C
    78% (32)
  • D
    2% (1)

Explanation

When a team signals a potential miss mid-Iteration, the Product Owner's proper response is to ensure the Iteration Backlog is accurately prioritized so the most valuable work gets completed first - if anything must be dropped, it should be the lowest-priority items, not high-value ones. This is a core PO accountability in SAFe: you can't always control what gets done, but you control what gets done first.

Why the distractors are wrong:

  • A is wrong because Innovation and Planning (IP) Iterations are fixed cadence events at the end of a PI, not a rescue mechanism to be inserted ad hoc.
  • B is wrong because adding people mid-iteration typically slows the team down (Brooks' Law) and the System Team has its own PI commitments.
  • D is wrong because splitting a Story into a "coding story" and a "testing story" and deferring the test violates SAFe's Definition of Done and creates hidden technical debt - stories must be tested and accepted within the same Iteration.

Memory tip: Think of the PO as a traffic controller, not a firefighter. When the team is overwhelmed, the PO doesn't add lanes or call in backup - they make sure traffic flows in the right order so the most important cars get through.

Topics

#Product Owner#iteration commitment#backlog prioritization#iteration management