SAFE-SP · Question #26

3- If the PI System Demo shows the current state of the Solution, then who is this demo intended for?

The correct answer is B. The Business Owners. Business Owners are the correct audience because the PI System Demo is designed to show key stakeholders - those with financial and governance responsibility - the integrated, working solution at the end of a Program Increment, allowing them to evaluate business value and…

ART Execution

Question

3- If the PI System Demo shows the current state of the Solution, then who is this demo intended for?

Options

  • AThe Scrum Masters
  • BThe Business Owners
  • CThe Product Owner
  • DThe Agile Team

How the community answered

(27 responses)
  • B
    96% (26)
  • D
    4% (1)

Explanation

Business Owners are the correct audience because the PI System Demo is designed to show key stakeholders - those with financial and governance responsibility - the integrated, working solution at the end of a Program Increment, allowing them to evaluate business value and provide feedback that influences future PI planning.

Why the distractors are wrong:

  • A (Scrum Masters) - Scrum Masters facilitate team-level ceremonies and remove impediments; they are not the intended recipients of a business-value demonstration.
  • C (Product Owner) - Product Owners receive feedback at the iteration (team) demo level, not at the PI System Demo, which operates at the ART/Solution level.
  • D (Agile Team) - Agile Teams are the presenters of the work, not the intended audience; they built the solution being demonstrated.

Memory tip: Think of the "PI" in "PI System Demo" as standing for People with the Investment - Business Owners hold the budget and accountability for ROI, so they are the ones who need to see whether the solution is delivering business value at the Program level.

Topics

#PI System Demo#Business Owners#ART events#solution visibility