SAFE-SP · Question #11
Which activity happens in the Inspect and Adapt workshop?
The correct answer is A. A demo of the integrated system. Option A is correct because the Inspect and Adapt (I&A) workshop in SAFe begins with a PI System Demo, where all Agile Release Train (ART) teams demonstrate the integrated, working system built during the Program Increment - this is a defining activity of the event. Why the…
Question
Which activity happens in the Inspect and Adapt workshop?
Options
- AA demo of the integrated system
- BRefining the Program backlog
- CPlanning the next PI
- DA retrospective of the Iteration
How the community answered
(34 responses)- A94% (32)
- C3% (1)
- D3% (1)
Explanation
Option A is correct because the Inspect and Adapt (I&A) workshop in SAFe begins with a PI System Demo, where all Agile Release Train (ART) teams demonstrate the integrated, working system built during the Program Increment - this is a defining activity of the event.
Why the distractors are wrong:
- B (Refining the Program Backlog) happens continuously during the PI and is primarily a responsibility of Product Management, not a structured I&A activity.
- C (Planning the next PI) occurs in the separate PI Planning event, which follows the I&A but is a distinct ceremony.
- D (A retrospective of the Iteration) is performed at the Iteration level at the end of each sprint - the I&A does include a retrospective component, but it's a PI-level retrospective, not an iteration one.
Memory tip: Think of I&A as "show, reflect, improve" - it starts with a demo of what was built (show), moves into quantitative measurement (reflect), then a problem-solving workshop (improve). The demo of the integrated system anchors the whole workshop.