SNIA
S10-300 · Question #47
After lab testing a solution, which two deliverables should be presented to the implementation team? (Choose two.)
The correct answer is A. list of tested and approved versioning and code D. tested procedures and process for failover and redundancy. See the full explanation below for the reasoning.
Question
After lab testing a solution, which two deliverables should be presented to the implementation team? (Choose two.)
Options
- Alist of tested and approved versioning and code
- Bperformance metrics showing maximum performance
- Ccomplete TCO and ROI documentation for the solution
- Dtested procedures and process for failover and redundancy
How the community answered
(45 responses)- A82% (37)
- B7% (3)
- C11% (5)
Community Discussion
No community discussion yet for this question.