A customer has created a disaster recovery (DR) plan and is synchronously replicating its data to a remote facility. The remote storage/server needs to be configured (LUN masking, zoning, and…
The correct answer is C. pre-configure the remote storage/server, failover storage, start application. See the full explanation below for the reasoning.
Question
A customer has created a disaster recovery (DR) plan and is synchronously replicating its data to a remote facility. The remote storage/server needs to be configured (LUN masking, zoning, and rescanning the SCSI bus). To failover the application, what must the customer do?
Options
- Afailover storage, re-configure the remote storage/server, start application
- Bfailover storage, start application, re-configure the remote storage/server
- Cpre-configure the remote storage/server, failover storage, start application
- Dpre-configure the remote storage/server, start application, failover storage
How the community answered
(24 responses)- A4% (1)
- B13% (3)
- C79% (19)
- D4% (1)
Community Discussion