When planning a NAS solution, which two sub-processes are associated with Business Capacity Management for a NAS solution? (Choose two.)

The correct answer is A. develop financial forecast B. determine transaction trend. See the full explanation below for the reasoning.

Question

When planning a NAS solution, which two sub-processes are associated with Business Capacity Management for a NAS solution? (Choose two.)

Options

  • Adevelop financial forecast
  • Bdetermine transaction trend
  • Crun reports on the storage utilization and IOPS components
  • Dtransaction Unit equated to IOPS, block size, cache hit and network impact

How the community answered

(66 responses)
  • A
    80% (53)
  • C
    6% (4)
  • D
    14% (9)

Community Discussion

No community discussion yet for this question.