S10-210 · Question #76
A line of business (LOB) executive informs you that a new application requires 99.999% (five 9s) of up-time from both planned and unplanned outages before a service level objective (SLO) will be…
The correct answer is D. 6.06 seconds. See the full explanation below for the reasoning.
Question
A line of business (LOB) executive informs you that a new application requires 99.999% (five 9s) of up-time from both planned and unplanned outages before a service level objective (SLO) will be breached. What is the amount of permissible downtown per week?
Options
- A20.16 minutes
- B.605 seconds
- C5.04 minutes
- D6.06 seconds
How the community answered
(40 responses)- A5% (2)
- B3% (1)
- C10% (4)
- D83% (33)