Click the Exhibit button. Your company has purchased a new storage array that has dual management access network ports. You need to connect the array and provide maximum redundancy without affecting…

The correct answer is A. Cable one management access network port into management switch 1 and the other port. See the full explanation below for the reasoning.

Question

Click the Exhibit button. Your company has purchased a new storage array that has dual management access network ports. You need to connect the array and provide maximum redundancy without affecting production traffic. Referring to the exhibit, where should the ports be attached?

Exhibit

S10-210 question #22 exhibit

Options

  • ACable one management access network port into management switch 1 and the other port
  • BCable both management access network ports into management switch 2.
  • CCable one management access network port into core switch 1 and the other into core
  • DCable both management access network ports into management switch 1.

How the community answered

(42 responses)
  • A
    83% (35)
  • B
    10% (4)
  • C
    5% (2)
  • D
    2% (1)