nerdexam
SNIA

S10-210 · Question #56

Click the Exhibit button. Referring to the configuration shown in the exhibit, when will the servers oversubscribe the connections between the storage array and the switch?

The correct answer is A. When the 6th server is added to the configuration. See the full explanation below for the reasoning.

Question

Click the Exhibit button. Referring to the configuration shown in the exhibit, when will the servers oversubscribe the connections between the storage array and the switch?

Exhibit

S10-210 question #56 exhibit

Options

  • AWhen the 6th server is added to the configuration
  • BWhen the 7th server is added to the configuration
  • CWhen the 8th server is added to the configuration
  • DWhen the 9th server is added to the configuration

How the community answered

(66 responses)
  • A
    73% (48)
  • B
    15% (10)
  • C
    5% (3)
  • D
    8% (5)

Community Discussion

No community discussion yet for this question.

Full S10-210 Practice