A business analyst has just been informed by her project manager that a baselined requirement is going to be dropped from the set, to complete the project within a shorter timescale. Which elements…

The correct answer is B. Requirements cross-referencing, Change control. See the full explanation below for the reasoning.

Question

A business analyst has just been informed by her project manager that a baselined requirement is going to be dropped from the set, to complete the project within a shorter timescale. Which elements of requirements management will require attention in response to this event?

Options

  • ARequirements identification, Requirements cross-referencing.
  • BRequirements cross-referencing, Change control.
  • CChange control, Requirements origin and ownership.
  • DChange control, Requirements identification.

How the community answered

(52 responses)
  • A
    12% (6)
  • B
    81% (42)
  • C
    2% (1)
  • D
    6% (3)

Community Discussion

No community discussion yet for this question.