RE18 · Question #78
RE18 Question #78: Real Exam Question with Answer & Explanation
The correct answer is B. Requirements cross-referencing, Change control.. See the full explanation below for the reasoning.
Question
A business analyst has just been informed by her project manager that a baselined requirement is going to be dropped from the set, to complete the project within a shorter timescale. Which elements of requirements management will require attention in response to this event?
Options
- ARequirements identification, Requirements cross-referencing.
- BRequirements cross-referencing, Change control.
- CChange control, Requirements origin and ownership.
- DChange control, Requirements identification.