RE18 · Question #77
A developer working to implement a set of baselined requirements has called the business analyst responsible for the project to check her understanding of a key requirement. During the conversation…
The correct answer is A. Configuration management. See the full explanation below for the reasoning.
Question
A developer working to implement a set of baselined requirements has called the business analyst responsible for the project to check her understanding of a key requirement. During the conversation, it becomes clear to both parties that the developer is working on an older version of the requirement. Which element of requirements management has failed?
Options
- AConfiguration management.
- BChange control.
- CRequirements identification.
- DRequirements cross-referencing.
How the community answered
(29 responses)- A76% (22)
- B14% (4)
- C7% (2)
- D3% (1)