The following requirements have been elicited during an interview with the warehousing manager: REQ#1 - The system shall allow inventory levels to be modified to reflect stock wastage. REQ#2 - The…

The correct answer is B. Overlapping. See the full explanation below for the reasoning.

Question

The following requirements have been elicited during an interview with the warehousing manager: REQ#1 - The system shall allow inventory levels to be modified to reflect stock wastage. REQ#2 - The system will automatically reorder stock that has fallen below the minimum reorder level. What kind of requirements are these?

Options

  • AConflicting.
  • BOverlapping.
  • CInconsistent.
  • DIrrelevant.

How the community answered

(43 responses)
  • A
    9% (4)
  • B
    72% (31)
  • C
    5% (2)
  • D
    14% (6)