RE18 · Question #15

A business analyst working on a project has identified: 3 requirements for which there is a workaround and the users can live without; 2 requirements that the users can live without for now; 15…

The correct answer is D. W. See the full explanation below for the reasoning.

Question

A business analyst working on a project has identified: 3 requirements for which there is a workaround and the users can live without; 2 requirements that the users can live without for now; 15 requirements which, if not delivered, will make the solution unworkable or useless. When these requirements are prioritized using MoSCoW, which of the following categories will not be used?

Options

  • AM
  • BS
  • CC
  • DW

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    5% (2)
  • C
    14% (6)
  • D
    79% (34)