RE18 · Question #15
A business analyst working on a project has identified: 3 requirements for which there is a workaround and the users can live without; 2 requirements that the users can live without for now; 15…
The correct answer is D. W. See the full explanation below for the reasoning.
Question
A business analyst working on a project has identified: 3 requirements for which there is a workaround and the users can live without; 2 requirements that the users can live without for now; 15 requirements which, if not delivered, will make the solution unworkable or useless. When these requirements are prioritized using MoSCoW, which of the following categories will not be used?
Options
- AM
- BS
- CC
- DW
How the community answered
(43 responses)- A2% (1)
- B5% (2)
- C14% (6)
- D79% (34)