A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'. What element of…

The correct answer is A. Change control. See the full explanation below for the reasoning.

Question

A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'. What element of requirements management will offer this?

Options

  • AChange control
  • BConfiguration control
  • CConfiguration management
  • DSoftware support

How the community answered

(47 responses)
  • A
    81% (38)
  • B
    2% (1)
  • C
    6% (3)
  • D
    11% (5)