nerdexam
BCS-ISEB

RE18 · Question #14

RE18 Question #14: Real Exam Question with Answer & Explanation

Sign in or unlock RE18 to reveal the answer and full explanation for question #14. The question stem and answer options stay visible for context.

Question

A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'. What element of requirements management will offer this?

Options

  • AChange control
  • BConfiguration control
  • CConfiguration management
  • DSoftware support

Unlock RE18 to see the answer

You've previewed enough free RE18 questions. Unlock RE18 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full RE18 Practice
A project manager has stated that he wants 'secure and controlled... | RE18 Q#14 Answer | NerdExam