RCDDV15 · Question #79

Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client's need? (Select two options.)

The correct answer is A. Preliminary budget numbers E. Time constraints and/or milestones. Preliminary budget numbers (A) and time constraints/milestones (E) are correct because identifying the best solution for a client requires understanding the two most fundamental project constraints: what they can afford and when they need it delivered. Without these, a designer…

ICT Distribution Design Process

Question

Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client's need? (Select two options.)

Options

  • APreliminary budget numbers
  • BColor scheme for dropcables
  • CDocumentation plan
  • DRecommendations for label design of outlets
  • ETime constraints and/or milestones

How the community answered

(25 responses)
  • A
    76% (19)
  • B
    12% (3)
  • C
    8% (2)
  • D
    4% (1)

Explanation

Preliminary budget numbers (A) and time constraints/milestones (E) are correct because identifying the best solution for a client requires understanding the two most fundamental project constraints: what they can afford and when they need it delivered. Without these, a designer cannot meaningfully evaluate or compare solutions, since a technically ideal option may be unaffordable or impossible to deploy within the required timeframe.

Color scheme for dropcables (B) and label design recommendations for outlets (D) are wrong because these are granular aesthetic or administrative details that apply after a solution has already been selected, not inputs that help determine which solution is best. Documentation plan (C) is also wrong because it describes how the project will be recorded, not what the client actually needs or can accommodate.

Memory tip: Think of A and E as the two "feasibility filters" -- budget tells you what is affordable, and timeline tells you what is achievable. Any solution that fails either filter is not the best solution, regardless of its technical merits.

Topics

#client needs analysis#preliminary budget#milestones#design solutions