RCDDV15 · Question #52
An RFQ usually provides more detail than RFP in selection material such as
The correct answer is B. color. Color is a physical selection characteristic that precisely identifies a specific product variant, and an RFQ (Request for Quotation) goes into this level of exact specification because the buyer already knows exactly what they want and needs a price on it - color included…
Question
An RFQ usually provides more detail than RFP in selection material such as
Options
- Adelivery date
- Bcolor
- Cmake
- Dmounting option
How the community answered
(49 responses)- A16% (8)
- B73% (36)
- C8% (4)
- D2% (1)
Explanation
Color is a physical selection characteristic that precisely identifies a specific product variant, and an RFQ (Request for Quotation) goes into this level of exact specification because the buyer already knows exactly what they want and needs a price on it - color included. Delivery date (A) is a logistical term that belongs to fulfillment requirements present in both RFQs and RFPs, not a distinguishing detail of selection material. Make (C) refers to the manufacturer or brand and is typically captured in both document types as a baseline requirement rather than something an RFQ uniquely elaborates on. Mounting option (D) is a functional or installation specification that can appear in either document type and does not represent the kind of granular visual/physical selection detail where RFQs stand apart.
Memory tip: Think of an RFQ as a shopping list for an exact item - you already know the brand, the size, and yes, the color. Color is the kind of finish-level detail that separates one SKU from another, which is precisely why a quote request spells it out.