A project's closeout plan will be executed by the project manager (PM) and will be managed and approved by the
The correct answer is C. lCT distribution designer. In ICT infrastructure projects, the closeout plan is managed and approved by the ICT distribution designer because this person created the original design specifications and is therefore the appropriate authority to verify that the installed system matches those specifications…
Question
A project's closeout plan will be executed by the project manager (PM) and will be managed and approved by the
Options
- Aowner
- Bcontractor
- ClCT distribution designer
- Dprojects installation supervisor
How the community answered
(32 responses)- A3% (1)
- B9% (3)
- C81% (26)
- D6% (2)
Explanation
In ICT infrastructure projects, the closeout plan is managed and approved by the ICT distribution designer because this person created the original design specifications and is therefore the appropriate authority to verify that the installed system matches those specifications and that all documentation is complete and accurate. The owner (A) is the client who receives the finished project and its documentation, but does not manage or technically approve the closeout process itself. The contractor (B) executes the installation work and participates in closeout activities, but lacks the design authority required to formally approve the closeout plan. The projects installation supervisor (D) oversees on-site work during the build phase, but that supervisory role ends with installation rather than extending to formal closeout approval.
Memory tip: Think of the designer as the "design authority" -- only the person who set the design standards can confirm that the project has truly met them, making the ICT distribution designer the logical approver at closeout.