RCDDV15 · Question #280
As a project manager, what should the FINAL task be at of the end of each project?
The correct answer is C. A lessons learned meeting. A lessons learned meeting (C) is the final task because it captures what went right, what went wrong, and how future projects can improve - this institutional knowledge is the lasting deliverable that benefits the entire organization beyond the current project. Why the…
Question
As a project manager, what should the FINAL task be at of the end of each project?
Options
- AA costing and billing review
- BDelivery of the final documentation
- CA lessons learned meeting
- DA sign off meeting with the owner
How the community answered
(22 responses)- A9% (2)
- B5% (1)
- C82% (18)
- D5% (1)
Explanation
A lessons learned meeting (C) is the final task because it captures what went right, what went wrong, and how future projects can improve - this institutional knowledge is the lasting deliverable that benefits the entire organization beyond the current project.
Why the distractors are wrong:
- A (Costing/billing review): Financial reconciliation happens during project closeout, not as the final step - it informs the lessons learned, not the other way around.
- B (Final documentation delivery): Documentation is completed before closeout activities; it's an input to the closing phase, not the capstone.
- D (Sign-off meeting with owner): Owner sign-off marks formal acceptance of deliverables, which occurs before the project is truly closed out - lessons learned come after.
Memory tip: Think of the lessons learned meeting as the project's "autopsy" - you can only perform it after everything else (delivery, billing, sign-off) is done, making it naturally last. The acronym LAST can help: Lessons learned = After Sign-off and Transition.