Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?

The correct answer is A. Locating of other utilities. See the full explanation below for the reasoning.

Outside Plant Design

Question

Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?

Options

  • ALocating of other utilities
  • BBonding and grounding of metallic conductors
  • CFees calculated on distance
  • DBuilding entrance conduit plugging

How the community answered

(28 responses)
  • A
    82% (23)
  • B
    4% (1)
  • C
    4% (1)
  • D
    11% (3)