BICSI
RCDDV15 · Question #257
Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?
The correct answer is A. Locating of other utilities. See the full explanation below for the reasoning.
Outside Plant Design
Question
Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?
Options
- ALocating of other utilities
- BBonding and grounding of metallic conductors
- CFees calculated on distance
- DBuilding entrance conduit plugging
How the community answered
(28 responses)- A82% (23)
- B4% (1)
- C4% (1)
- D11% (3)
Topics
#outside plant#buried pathway#right-of-way permit#utility locating