At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?
The correct answer is A. The project is under budget. See the full explanation below for the reasoning.
Question
At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?
Options
- AThe project is under budget.
- BThe project is budget incorrect.
- CThe project has been back-end loaded.
- DThe project is over budget.
How the community answered
(47 responses)- A70% (33)
- B4% (2)
- C17% (8)
- D9% (4)