BICSI
RCDD-001 · Question #161
What is the PERT estimate of time for cable placement on a given job? - Optimistic time is 100 hours - Most likely time is 125 hours - Pessimistic time is 210 hours
The correct answer is C. 135 hours. See the full explanation below for the reasoning.
Question
What is the PERT estimate of time for cable placement on a given job?
- Optimistic time is 100 hours
- Most likely time is 125 hours
- Pessimistic time is 210 hours
Options
- A100 hours
- B125 hours
- C135 hours
- D155 hours
- E175 hours
How the community answered
(49 responses)- A2% (1)
- B4% (2)
- C78% (38)
- D6% (3)
- E10% (5)
Community Discussion
No community discussion yet for this question.