When the Product Owner is too busy to work with all of the teams in a multi-team product development effort, which strategy will help them? (Choose the best answer)

The correct answer is B. Communicate a clear Product Goal and delegate some activities to the Developers. The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. They are also accountable for effective Product Backlog management, which includes clearly expressing Product Backlog items, ordering them to best achieve goals…

Product Management

Question

When the Product Owner is too busy to work with all of the teams in a multi-team product development effort, which strategy will help them? (Choose the best answer)

Options

  • AAdd component team Product Owners.
  • BCommunicate a clear Product Goal and delegate some activities to the Developers.
  • CEnlist the Program Management Office to help coordinate work.
  • DAssign sub-Product Owners to each Scrum Team.
  • EAll of the above.

How the community answered

(17 responses)
  • A
    6% (1)
  • B
    82% (14)
  • D
    12% (2)

Explanation

The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. They are also accountable for effective Product Backlog management, which includes clearly expressing Product Backlog items, ordering them to best achieve goals and missions, ensuring that the Product Backlog is transparent, visible and understood. The Product Owner may do the above work or may delegate the responsibility to others. However, the Product Owner remains accountable. When working with multiple Scrum Teams on the same product, the Product Owner should ensure that there is a shared understanding of the Product Goal among all the teams and stakeholders. The Product Goal is the long-term objective for the Scrum Team. They must fulfill (or abandon) one objective before taking on the next. The Product Owner should also collaborate with the Developers to create and refine Product Backlog items that are valuable, feasible, and testable. The Developers are accountable for creating a plan for the Sprint, the Sprint Backlog. The Product Owner should trust the Developers to self-organize and deliver the most valuable increments possible.

Topics

#Product Goal#multi-team scaling#delegation#Product Owner capacity