PSPO-I · Question #104
What activities would a Product Owner typically undertake in the period between the end of the current Sprint and the start of the next Sprint? (choose the best answer)
The correct answer is B. Refine the Product Backlog. the Product Owner is responsible for refining the Product Backlog, which is an ongoing activity that can occur at any time, including between Sprints. The other options are not typical activities for the Product Owner between Sprints, as the next Sprint starts immediately after…
Question
What activities would a Product Owner typically undertake in the period between the end of the current Sprint and the start of the next Sprint? (choose the best answer)
Options
- AThere are no such activities. The next Sprint starts immediately after the current
- BRefine the Product Backlog.
- CUpdate the project plan with stakeholders.
- DWork with the Quality Assurance departments on the Increment of the current Sprint.
How the community answered
(42 responses)- B95% (40)
- C2% (1)
- D2% (1)
Explanation
the Product Owner is responsible for refining the Product Backlog, which is an ongoing activity that can occur at any time, including between Sprints. The other options are not typical activities for the Product Owner between Sprints, as the next Sprint starts immediately after the current Sprint1, the project plan is replaced by the Product Backlog2, and the Quality Assurance is done by the Developers of the Scrum Team within the Sprint1. 1: The Scrum Guide | Scrum.org 2: What is a Product Backlog? | Scrum.org
Topics