The long-term (more than 60 days) process of restoration activities after an emergency or disaster that returns the organization to its pre-event condition is called:
The correct answer is C. Business resumption. See the full explanation below for the reasoning.
Question
The long-term (more than 60 days) process of restoration activities after an emergency or disaster that returns the organization to its pre-event condition is called:
Options
- ABusiness continuity
- BBusiness recovery
- CBusiness resumption
- DBusiness healing
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C75% (21)
- D14% (4)