Contingency planning is the result of which four major components?

The correct answer is B. emergency response, crisis management, business recovery, business resumption. See the full explanation below for the reasoning.

Question

Contingency planning is the result of which four major components?

Options

  • Aemergency response, crisis management, pressure devices, risk analysis
  • Bemergency response, crisis management, business recovery, business resumption
  • Cbasic planning, crisis management, business recovery, business resumption
  • Dunder investigation, crisis management, business recovery, pressure devices

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    71% (17)
  • C
    17% (4)