Introductory Info Additional Information A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the…

The correct answer is B. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report. C. The Change Authority will report monthly to the Project Manager on the status of the change budget. Explanation/Reference:

Risk

Question

Introductory Info Additional Information A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now. The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced. The contract is to be reviewed and Portraits Ltd reminded of their agreement. The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project. Which 2 statements should be recorded under either the Records or Reporting headings?

Options

  • AProject Support will maintain the Risk Register.
  • BThe evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report.
  • CThe Change Authority will report monthly to the Project Manager on the status of the change budget.
  • DRisks that are likely to occur within the next two weeks should be recorded as imminent.
  • EA summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board.

How the community answered

(42 responses)
  • A
    14% (6)
  • B
    79% (33)
  • D
    5% (2)
  • E
    2% (1)

Explanation

Explanation/Reference:

Topics

#Risk Register#Highlight Report#Change Authority#risk reporting