Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?

The correct answer is D. Project Assurance. Explanation/Reference:

Risk

Question

Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?

Options

  • AProject Support
  • BProject Manager
  • CTeam Manager
  • DProject Assurance

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    9% (3)
  • C
    3% (1)
  • D
    82% (28)

Explanation

Explanation/Reference:

Topics

#Project Assurance#risk management strategy#assurance role#organization theme