Introductory Info Scenario: The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document…
The correct answer is A. None because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project. Explanation/Reference:
Question
Introductory Info Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process. What additional risk will this place on the project?
Options
- ANone because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project.
- BThese changes will delay stage 3 by three weeks.
- CThere is only ?0k left in the project change budget.
- DThe reduced value of the contracted services required by the Outsourcing project may result in an insufficient number of proposals being received.
How the community answered
(49 responses)- A78% (38)
- B6% (3)
- C12% (6)
- D4% (2)
Explanation
Explanation/Reference:
Topics
Community Discussion
No community discussion yet for this question.