PRINCE2-AGILE-FOUNDATION · Question #9
Which artifact is used to describe the project's major products in the form of epic user stories?
The correct answer is D. Project backlog. The Project Backlog is the artifact used to describe the project's major products in the form of epic user stories. Epic stories are large, high-level user stories that capture significant features or product components that may later be decomposed into smaller, more detailed…
Question
Which artifact is used to describe the project's major products in the form of epic user stories?
Options
- AProject dashboard
- BRelease map
- CProduct backlog
- DProject backlog
How the community answered
(28 responses)- A4% (1)
- B11% (3)
- C4% (1)
- D82% (23)
Explanation
The Project Backlog is the artifact used to describe the project's major products in the form of epic user stories. Epic stories are large, high-level user stories that capture significant features or product components that may later be decomposed into smaller, more detailed user stories in the product backlog. The Project Backlog provides a strategic view of what the project intends to deliver and supports planning at the project level, including releases and stages. It bridges the gap between business requirements and team-level delivery.