PRINCE2-AGILE-FOUNDATION · Question #11

Which artifact identifies risks associated with using an iterative project management approach?

The correct answer is B. Agilometer. The Agilometer is a diagnostic tool used within PRINCE2 Agile to assess the agility maturity and identify risks associated with adopting or operating in an iterative and agile environment. It helps teams and organizations evaluate their current agile capabilities, cultural…

Agile Techniques and Behaviors

Question

Which artifact identifies risks associated with using an iterative project management approach?

Options

  • AProject backlog
  • BAgilometer
  • CRisk management approach
  • DDefinition of Done

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    85% (23)
  • C
    4% (1)
  • D
    4% (1)

Explanation

The Agilometer is a diagnostic tool used within PRINCE2 Agile to assess the agility maturity and identify risks associated with adopting or operating in an iterative and agile environment. It helps teams and organizations evaluate their current agile capabilities, cultural readiness, and potential challenges that may impact project delivery. The Agilometer highlights risk areas such as resistance to change, lack of agile skills, unclear roles, or insufficient governance adaptation. By providing a structured assessment, it enables proactive risk management and targeted improvements to reduce uncertainties inherent in iterative approaches.

Topics

#agilometer#risk assessment#iterative approach#agile artifacts