PRINCE2-AGILE-FOUNDATION · Question #52

How does agile address the risk associated with the project not being fully understood at the beginning?

The correct answer is D. By preventing the analysis of details at the start. You've hit your limit · resets 5am (America/New_York)

PRINCE2 Agile Behaviors and Concepts

Question

How does agile address the risk associated with the project not being fully understood at the beginning?

Options

  • ABy allowing a lot of detail at the start
  • BBy avoiding too much detail at the start
  • CBy requiring details at the start
  • DBy preventing the analysis of details at the start

How the community answered

(22 responses)
  • A
    5% (1)
  • D
    95% (21)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#agile risk management#iterative delivery#requirements uncertainty#project startup